Roger Dudman Way would close to through traffic for about 20 months while Network Rail builds a new platform and western entrance at Oxford station, due by summer 2029.

Roger Dudman Way would close to through traffic for around 20 months while Network Rail builds a new platform and a western entrance at Oxford station. Network Rail set out the plans on Thursday 26 November. It is aiming to open both by summer 2029.

That date depends on two things, Network Rail says: the funding being released and the main construction contract being awarded. Neither has happened yet.

What the closure means for Roger Dudman Way

The road would shut to through traffic under what Network Rail calls an “indicative programme”. The dates are not fixed. During the closure:

  • people on foot and on bikes could still use the road
  • a diversion would be set up for vehicles that need local access
  • a temporary footbridge would keep access to and from Roger Dudman Way
  • the road would be diverted to the north

The closure is needed to build new road and rail bridges at Sheepwash and to move utility pipes and cables out of the way. Network Rail says it is looking at ways to shorten it, including some work around the clock where that is appropriate.

Botley Road and its pavements are expected to stay open throughout. Botley Road reopened in September after three and a half years shut for the bridge replacement.

Tom Pierpoint, industry programme director for Network Rail’s Great Western route, said: “We know delivering the next phase of the upgrade will have an impact locally, particularly around Roger Dudman Way. We’re looking carefully at how we can reduce that disruption and will keep residents and businesses informed as the plans develop.”

When the work would happen

Network Rail’s notes to editors give this outline:

Stage When
Preparatory work Early 2027
Western entrance design through planning By mid-2027
Bridges and new platform After the preparatory work
Western entrance construction 2028 and 2029
New platform and entrance open Target summer 2029

Details of piling and other construction work will be shared with residents once the programme is finalised, Network Rail says.

What the western entrance would have

Design work on the entrance has restarted. It is being updated to match the latest forecasts of passenger numbers, including journeys linked to East West Rail and the Universal resort planned in Bedfordshire.

The current proposals include:

  • ticket machines
  • ticket gates
  • toilets

Cycle parking and a pick-up and drop-off area are also being considered.

The extra through platform would give room for more trains. Network Rail names East West Rail and possible services between Cowley and London Marylebone, if the Cowley Branch Line reopens. It says no new timetable is being announced as part of this update.

Work finishing off now

Before the next stage starts, Network Rail is completing work from the Botley Road project:

  • finishing the temporary junction from Cripley Road to Roger Dudman Way
  • replacing temporary railings with permanent ones
  • repairing paving in Frideswide Square
  • building a new southern walkway along Botley Road, overnight

The bigger plan, and when you can comment

The platform and western entrance are separate from Network Rail’s longer-term ideas for the station. Those could include a new eastern entrance, a cycle hub, better links to buses and other transport, and development around Beckett Street. Architects were appointed earlier this month to draw up that masterplan.

A public consultation on those wider proposals is provisionally planned for late May to early July 2027.

What it means for you

  • If you live or work off Roger Dudman Way, expect a long closure to through traffic once the main works start, with local access kept by a diversion. No start date has been given. Network Rail says it will write directly to people affected.
  • If you walk or cycle that way, the route stays open, with a temporary footbridge.
  • If you use Botley Road, it is expected to stay open throughout.
  • If you want to ask a question or raise a concern, the project team’s address is OxfordFeedback@networkrail.co.uk.

Source: Network Rail, Oxford station upgrade moves forward with plans for new platform and western entrance, 26 November 2026.