Plans for the £8m Covered Market upgrade are open for comment until 24 December. They include new shop space, more toilets, solar panels and a new substation.

Oxford City Council has applied for planning permission for its £8 million upgrade of the Covered Market. The plans would create new space for shops, double the number of women’s toilets and put solar panels on the roof.

The council owns the market. It announced the application on Wednesday 25 November. Comments can be made until Thursday 24 December.

Overview

  • What: a full planning application and a listed building consent application for the Covered Market, Market Street, OX1 3DZ
  • Cost: £8 million, according to the council
  • Comment by: Thursday 24 December 2026
  • Decision due: by 14 January 2027, the council’s target date
  • Building work: expected to start in 2028

What the plans include

The two applications are 26/02495/FUL for planning permission and 26/02496/LBC for listed building consent. Both describe the same work:

  • demolishing the public toilets off Market Street and the buildings in the service yard
  • a new internal atrium
  • a new substation building and staff toilets in the service yard
  • new public toilets
  • new gates at the entrances, with signs
  • work on existing shop units and new areas for shops
  • a rooftop walkway and a new electrical network, with solar panels on the roof
  • new paving throughout, redecoration of the structure and the underside of the roof, and new lighting
  • cycle parking

The council’s announcement says moving the existing substation is “a key part” of the project, because it frees up space for new shops. It says the women’s toilets will double in number.

The electrical work is meant to give the council more control over the market’s supply and “help to prevent future disruption to businesses”. The solar panels would help power the market’s public areas.

When the work would happen

The applications were received on 15 October and validated on 19 November, the planning records show.

The council says detailed surveys are due to start in January 2027. Construction is “currently expected to start in 2028”. Traders will be involved throughout to keep disruption as low as possible, it said.

The council’s announcement gives two timings for hiring a builder. The release says the council aims to appoint a contractor “early in the new year”. In the same release, council leader Susan Brown says the plan is “to appoint a contractor by the end of the year”.

Cllr Brown said: “Oxford’s Covered Market is a much-loved part of our city’s heritage, and we want to ensure it continues to thrive for generations to come.”

She added: “This work will make a real difference to the market, by creating more opportunities for independent businesses, improving facilities for visitors and investing in more reliable and sustainable infrastructure.”

What it means for you

  • If you want to comment, search for 26/02495/FUL on the council’s planning applications page. The neighbour consultation closes on Thursday 24 December. A press notice is due to run on 3 December.
  • If you shop at the market, nothing changes yet. Surveys begin in January and the main building work is not expected before 2028.
  • If you trade there, the council says it will keep working with traders as the plans move forward.